Progress of geothermal power generation projects under construction by Kaishan Group

  1、 Hungary Turawell Project:

  The installed capacity of the project is 3.35MW. It started construction in May 2017 and is currently in the final stage of equipment installation. It is planned to enter single machine equipment debugging by the end of October and power generation trial operation in November.

201710101681180

201710101681181.jpg

201710101681182

  2、 Wabuska Project in the United States:

  The project has an installed capacity of 6.3MW and started construction in June 2017. The first batch of power generation equipment arrived at the site in early October, and equipment installation began on October 7th. It is planned to complete the installation by the end of December and enter into single machine debugging and power generation trial operation.

201710101695855

201710101695856

  3、 Indonesia SMGP240MW Geothermal Power Project

  The installed capacity of the project is 240MW. Well drilling construction began in October 2016, and a total of 7 production wells on platform A have been completed; The main civil construction of the booster station and platform booster station of the project has been completed, and large equipment such as the main transformer have been installed on site one after another. The foundation of the transmission line tower has entered comprehensive construction; The first batch of power generation equipment for platform A will be transported to the site in September 2017. The plan is to complete the installation of the first batch of motor sets for platform A by the end of December and enter the equipment for single machine debugging.

  The current drilling depth of the first well on platform D has exceeded 1000m; Platform C drilling rig enters the site for assembly, with plans to start drilling in late October;

2017101016102959

20171010161014419

  4、 Indonesia Sokoria 30MW Geothermal Power Project

  The installed capacity of the project is 30MW, and the land purchase and earthwork construction for the production well platform and on-site roads have been completed. The drilling of the production well began on October 8th.

20171010161225154

20171010161245647